The wing system routing (Section 19) is now complete. Also most of the work on the aileron actuation ( section (23) is done, but not permanently installed.
The lower wing skin is also all ready to be riveted on, but it will delayed until flap and aileron is finished.
The flap section is also nearing completion. I started the riveting today. Should be completed by end of this week.
I also work on the avionic and electric schematic. This is an example for the left wing
|
Left wing were the pitot tube will be. |
|
The heated pitot tube. |
|
Inboard left wing. The connector is for the GMU 22 magnetometer. |
|
Left wing root. The coiled cable is RG-400 Coax for the wing tip antenna (NAV/GS/LOC) |
|
Right wing trim servo |
|
Trim servo |
|
Right wing. Autopilot servo. |
|
Left and right flap structure |
|
Ready to rivet on the skins. |